The Carbon Reduction Plan template (PPN 006), section by section
The government's Carbon Reduction Plan (CRP) template is a short form with six sections. This page goes through each one: what the template asks for, the rule behind it, and what a small supplier usually writes.
Who has to submit one
PPN 006 replaced PPN 06/21 for procurements under the Procurement Act 2023, which took effect on 24 February 2025. It applies to central government departments, their executive agencies and non-departmental public bodies buying goods, services or works with an estimated value above £5 million a year (including VAT). Other public bodies may choose to use it, and the NHS applies its own version to far more contracts. Where it applies, the CRP is a condition of participation: the plan isn't scored against other bidders, it either meets the standard or it doesn't.
The six sections, in order
The template (2025-04-16 version, .odt) opens with your supplier name and the publication date, then:
1. Commitment to achieving net zero
One sentence: [Supplier name] is committed to achieving net zero emissions by 20XX.
The year must be 2050 or earlier. The technical standard sets the UK as the minimum boundary; a global boundary also meets it.
2. Baseline emissions footprint
Your baseline year, a box for additional details relating to the baseline emissions calculations
, and a table of Scope 1, Scope 2, Scope 3 (included sources) and the total, in tCO2e.
If you have never measured before, the template's guidance notes say to state this and use your first reporting period as your baseline
. The details box is where you say that, which boundary you used (operational control for most small firms), and why any Scope 3 category is zero.
3. Current emissions reporting
The same table for your latest full reporting year. Use the same reporting period throughout the plan; the technical standard asks you to update the plan within six months of your financial year end.
4. Emissions reduction targets
Your targets, and a projection: We project that carbon emissions will decrease over the next five years to XX tCO2e by 20XX. This is a reduction of XX%.
The guidance suggests a graph of progress against target. If this is your first footprint, you set targets for the first time here.
5. Carbon reduction projects
Two lists: completed initiatives since the baseline, with the total reduction they achieved (in tCO2e and as a percentage of the baseline) and a statement that they'll be in effect when performing the contract; and future initiatives. The guidance gives examples: ISO 14001 or PAS 2060, joining SBTi, LED lighting and motion sensors, a travel policy that cuts flights, or electrifying the fleet. Both lists are for information only
.
6. Declaration and sign off
Fixed wording saying the plan follows PPN 006 and its reporting standard, the GHG Protocol corporate standard and the government's conversion factors, and that it was reviewed and signed off by the board of directors (or equivalent management body)
.
The technical standard adds the details: the plan must state that approval was given and the date, and it must be signed off by a director (or a designated member of an LLP) with their name and job title. A physical signature isn't needed, but the plan should clearly say it has been signed.
The rules behind the numbers
- Scope 1 and 2: all of them. Gas and other fuels you burn, fuel for vehicles you own or lease, refrigerant leaks, and the electricity and heat you buy.
- Scope 3: five categories only: upstream transport, waste, business travel, commuting and downstream transport.
- Gases and units: the seven Kyoto gases, reported as tonnes of CO2 equivalent, using the UK Government conversion factors.
- Boundary: financial control, operational control or equity share, as in the GHG Protocol. There's no requirement to have your footprint audited.
- Publishing: on your UK website, with a link in a prominent place on your homepage. Keep earlier plans online. If you don't have a website, you must send a copy to anyone who asks within 30 days.
- Parent company plans: allowed only if the parent wholly owns the bidder, the plan says the commitment applies to the bidder, its measures can be applied by the bidder on the contract, and it's published on the bidder's own website.
Filling it in without a consultant
For most small firms the data is already in the filing cabinet: twelve months of gas and electricity bills, fuel card statements or mileage logs, the waste contractor's annual report, travel expense claims, and a rough idea of how staff get to work. The builder takes those figures, applies the DESNZ factor for each year, writes each section in the template's wording and order, and adds an annex showing every factor's row in the government spreadsheet. Here's a worked example.
Sources: PPN 006, its guidance, technical standard and template (Cabinet Office / Government Commercial Agency, updated 10 July 2025).