A Carbon Reduction Plan example for a small business

This is a full Carbon Reduction Plan for Larchfield Facilities Ltd, a made-up 12-person cleaning and maintenance firm with an office, a small store and four vans. Every figure below came from the kind of records a firm like this already keeps, multiplied by the UK Government (DESNZ) conversion factor for that year.

The company, its people and its figures are invented. In the builder, "Fill in the example" loads this data so you can change it.

The result

tCO2e2023 (baseline)2025 (reporting year)
Scope 125.1415.83
Scope 24.434.74
Scope 3 (included sources)13.3512.15
Total42.9232.72

Total emissions fell 24%, mostly because two of the four diesel vans were replaced with electric vans. Electricity went up (21,400 to 26,800 kWh) because the vans now charge at the depot, which is exactly where PPN 006 wants that energy counted: Scope 2, not Scope 1. The firm commits to net zero by 2045, with a milestone of a 50% cut against the 2023 baseline by 2030. Projected on that line, emissions reach 21.46 tCO2e in 2030.

Where each 2025 figure came from

Factor = kilograms of CO2e per unit, from the DESNZ 2025 flat file, sheet "Factors by Category". The row number lets anyone check it in the spreadsheet.

SourceQuantityFactorRowtCO2e
Scope 1
Natural gas (office and store bills)31,200 kWh0.18296835.71
Diesel vans, Class II (mileage log)27,000 miles0.3099619768.37
Electric vans, Class II (charging counted in Scope 2)25,500 miles020000
Pool car, hybrid8,500 miles0.2063918361.75
Scope 2
Grid electricity, including van charging26,800 kWh0.17730664.74
Scope 3, category 4: upstream transport
Courier deliveries of supplies, van3,000 tonne-km0.631359571.89
Scope 3, category 5: waste
General waste to landfill1.2 tonnes520.5342610.62
General waste to energy recovery0.6 tonnes4.685684259<0.01
Paper and card, recycled0.9 tonnes4.685684398<0.01
Plastics, recycled0.4 tonnes4.685684328<0.01
Wastewater120 m³0.1708839460.02
Scope 3, category 6: business travel
National rail7,400 passenger-km0.0354654610.26
Staff cars on mileage claims, medium2,900 miles0.2787752570.81
Hotel nights, UK14 nights10.473950.15
Scope 3, category 7: commuting (12 staff, 215 days, 14 km each way)
Car (50% of staff)36,120 km0.1672553536.04
Electric car (10%)7,224 km0.0404753610.29
Bus (15%)10,836 passenger-km0.1038554531.13
Train (10%)7,224 passenger-km0.0354654610.26
Working from home2,000 hours0.3337886880.67
Scope 3, category 9: downstream transport
None. The plan gives the reason: the firm sells services on clients' sites and ships no goods.

Four things this example gets right that hand-made plans often miss

  1. A reason for every empty Scope 3 category. "0" with no explanation reads as "didn't check". One plain sentence is enough.
  2. The right factor year. The 2023 baseline uses the DESNZ 2023 set and 2025 uses the 2025 set. Grid electricity alone was 0.20707 kg/kWh in 2023 and 0.177 in 2025.
  3. Electric vehicles split correctly. Their miles are zero in Scope 1; the charging electricity is in Scope 2.
  4. Commuting estimated honestly. Headcount × days × distance × the share of each way of travelling, with the working shown. A staff survey is better, and the builder takes one as a pasted table.