NHS Carbon Reduction Plan requirements: the 2024 rules and April 2027

The NHS asks for carbon documents on far more contracts than central government does. Since April 2024 almost every new NHS procurement above the procurement threshold asks for either a full Carbon Reduction Plan or a Net Zero Commitment. From April 2027 the bar rises again.

Which document a tender asks for today

ProcurementWhat you need
£5 million a year or more (including VAT)A full Carbon Reduction Plan, aligned with PPN 006
New frameworks run by NHS bodies, whatever the contract value (where relevant and proportionate)A full Carbon Reduction Plan
Below £5 million a year and above the published procurement thresholdA Net Zero Commitment: a short public statement

NHS England says the CRP requirements align with those of central government's PPN 006, so any existing and current CRP developed according to the central government guidelines of PPN 006 will be accepted by the NHS. It should follow structure and length of central government's PPN 006 CRP template, though stylistic differences are acceptable.

What a full NHS plan must do

The questions in the tender

NHS bodies use four assessment questions (only question 2 when a Net Zero Commitment is enough). They're pass or fail, and plans aren't compared with each other.

  1. Confirm you have published a carbon reduction plan that meets the required reporting standard, and give the link.
  2. Confirm you're taking steps to reduce your emissions and are publicly committed to net zero by 2050, and give your target date.
  3. Baseline year, and Scope 1, 2 and 3 emissions for it.
  4. Reporting year, and Scope 1, 2 and 3 emissions for it.

The builder prints answers 2 to 4 in a box you can paste from.

What changes in April 2027

NHS England's net zero supplier roadmap says: From April 2027: The NHS will implement new proportionate requirements for suppliers to publicly report targets, emissions and publish a Carbon Reduction Plan for all of their relevant global scope 1, 2 and 3 emissions.

In plain terms, compared with today:

The detailed 2027 standard wasn't published on the NHS pages when this was checked (24 October 2026). Next on the roadmap: From April 2028, carbon footprints for individual products supplied to the NHS, and from 2030, published progress reports to qualify for contracts.

What to do now: get a clean PPN 006 plan in place, with good records behind it. A 2027-style footprint grows out of the same bills and logs, plus your purchase ledger. We'll add the 2027 format to the builder when NHS England publishes the details.

Evergreen

Separately, suppliers bidding for contracts or frameworks run by NHS England's Medicines Value and Access team need a valid Evergreen sustainable supplier assessment as well as a compliant carbon reduction plan. Evergreen is an online self-assessment run by NHS England, not a document you write.

Sources: Carbon reduction plan and net zero commitment requirements for the procurement of NHS goods, services and works (NHS England, version 3, 10 December 2025); Greener NHS: suppliers and the net zero supplier roadmap. Both read on 24 October 2026.

Not affiliated with the Cabinet Office, the Government Commercial Agency, NHS England or DESNZ. Quotes from PPN 006, its template and NHS England guidance are Crown copyright and reused under the Open Government Licence v3.0. Checked against the sources on 2026-10-24.