What contractors actually bid per item on county and town paving jobs, pulled from the public bid tabs and checked against them.

The sample: Fairfield County, Ohio, 2026

Two resurfacing jobs, every item with each bidder's unit price and the engineer's estimate. These 105 rows were checked by hand against the original PDFs: quantity × unit price equals the printed extension on every row, and each bidder's rows add up to the printed bid total.

FAI-CR7-3.390 Refugee Road Resurfacing Project

Fairfield County Engineer, Ohio · bids opened 2026-03-13 · awarded to The Shelly Company · 28 items, 84 rows · original tab (PDF)

ItemDescriptionUnitQtyEngineer's estimateThe Shelly Company (awarded)Kokosing Construction
202Wearing Course RemovedSY1,749$13.50$8.50$16.00
202Walk RemovedSF157$10.00$18.50$15.50
254Pavement Planing, Asphalt Concrete (1 1/2" Average Depth)SY38,645$2.13$2.05$4.00
407Non-Tracking Tack CoatGAL5,386$3.28$4.10$2.75
441Asphalt Concrete Surface Course, Type 1, (448), Pg70-22MCY2,806$190.00$213.00$222.00
617Compacted AggregateCY224$130.00$85.00$164.00
608Curb RampSF119$40.00$50.00$33.00
6085" Concrete WalkSF157$20.00$33.50$18.00
632Detector Loop, As Per PlanEA15$1,500.00$1,900.00$1,900.00
611Manhole Adjusted To GradeEA1$1,000.00$1,325.00$2,800.00
690Special - Asphalt Rejuvenating AgentSY67,344$1.25$1.25$1.25
690Special - TestingLS1$200.00$100.00$100.00
644Center LineMI4.96$4,761.00$4,370.00$4,370.00
644Edge Line, 4"MI8$2,885.00$2,780.00$2,780.00
644Stop LineLF306$15.00$7.95$7.95
644Channelizing Line, 8"LF2,710$2.50$1.90$1.90
644Crosswalk Line, 12"LF1,071$5.50$3.50$3.50
644Transverse/Diagonal LineLF810$7.80$7.35$7.35
644School Symbol Marking, 96"EA2$800.00$850.00$850.00
644Lane ArrowEA52$100.00$98.00$98.00
614Work Zone Center Line, Class Iii, 642 PaintMI4.96$420.00$1,025.00$935.00
614Work Zone Edge Line, Class Iii, 4", 642 PaintMI8$350.00$745.00$550.00
614Work Zone Channelizing Line, Class Iii, 8", 642 PaintLF2,710$1.00$0.89$0.80
614Work Zone Stop Line, Class Iii, 642 PaintLF306$5.00$7.25$3.50
614Work Zone Marking SignEA86$100.00$98.00$199.16
614Law Enforcement Officer W/ Patrol Car For AssistanceHR60$100.00$85.00$120.00
624MobilizationLS1$20,000.00$20,000.00$35,000.00
614Maintaining TrafficLS1$100,000.00$53,000.00$66,571.73
Total (matches the printed total on the tab)$1,023,992.69$1,031,305.65$1,187,980.99

Unit prices per item. Engineer's estimate is the county's own figure, printed on the same tab.

2026 Bloom Township Resurfacing Project

Fairfield County Engineer, Ohio · bids opened 2026-05-11 · awarded to The Shelly Company · 7 items, 21 rows · original tab (PDF)

ItemDescriptionUnitQtyEngineer's estimateThe Shelly Company (awarded)Law General Contracting
202Wearing Course RemovedSY144$17.50$37.50$3.00
254Pavement Planing, Asphalt Concrete, As Per PlanSY23,193$3.00$1.62$3.00
404LVT404 Lvt, Asphalt Concrete, Pg 64-22CY1,697$218.00$208.00$220.00
407Non-Tracking Track CoatGAL3,052$3.50$4.10$6.00
614Maintaining TrafficEA1$15,000.00$18,500.00$12,000.00
624MobilizationLS1$15,000.00$10,000.00$15,000.00
690Special - Asphalt Rejuvenating AgentSY40,674$1.25$1.25$1.33
Total (matches the printed total on the tab)$533,569.50$487,804.36$542,759.42

Unit prices per item. Engineer's estimate is the county's own figure, printed on the same tab.

The archive, honestly sized

The collector checks each owner's official bid-results page once a day, saves every new tab with its fetch time and the original file, and turns it into rows (item, unit, quantity, unit price, bidder, award, bid date, owner, link to the original). Today that is:

Tabs saved
104
Owners
6
Line-item rows
680
OwnerStateTabsLine-item rows
City of HastingsMN8saved, not yet parsed
Fairfield County EngineerOH14680
Lake County EngineerOH8saved, not yet parsed
Miami County EngineerOH24saved, not yet parsed
Tioga County Public WorksNY30saved, not yet parsed
Wyoming County Highway DepartmentNY20saved, not yet parsed

Only Fairfield's tabs are turned into rows so far; the others are saved as originals (several are scans) and listed in the tab index with their links.

Founding subscriber: $59/month

Subscribe for $59/monthCheckout by Polar (our merchant of record).
How the rows are checked

Each row's quantity times unit price must equal the extension printed on the tab (within $1). Separately, each bidder's extensions must add up to a total that is printed on the tab. Rows that fail either check keep the failure in their check and total_matches_printed columns instead of being silently fixed. Units are mapped only when the mapping is unambiguous (SY, LF, CY, TON, EA, LS, GAL...); anything else keeps the printed unit and is flagged unclear.

Sources and reuse

Every row comes from a bid tabulation the owner posted publicly on its own official website. The collector identifies itself, follows each site's robots.txt and waits between requests. Public bid results are public records; we link every row back to the original file so you can check it. Tomorrowish is not affiliated with any of these owners or bidders, and the original tab always wins if the two disagree. Spot an error? Tell us and we fix it.